2009 ENVIRONMENTAL PLAN

Performance Report

PROGRAMME TITLE TARGET RESULT

Intercomparison of the Air Quality Monitoring Assess the uncertainty of simultaneous measurements ACHIEVED
Network (AQMN) Analysers of HC5, CO, SO2, NOx and O3 with AQMN analysers ACHIEVED

Assessment of the Air Quality in Artemis Perform at least one year's worth of air quality ACHIEVED
monitoring with the mobile station of the AQMN in ACHIEVED
Artemis ACHIEVED

Recycling Programme at the Schools of the Collect at minimum 20 tonnes of recyclables (paper &
Municipality of Artemis aluminium cans) from the schools in the Municipality
of Artemis by the end of 2009
Preservation of Vravrona Wetlands
Provision of clean-up, signage, path development and
Display of Noise Data and Receiving Noise other works at the Vravrona wetlands in cooperation
Complaints through the Internet with the Hellenic Ornithological Society

Display noise data over the Internet and receive noise
complaints via AIA’s web site

2010 ENVIRONMENTAL PLAN

Objectives

PROGRAMME TITLE TARGET

Wildlife Hazard Control and Reduction Programme Revision Minimise wildlife strike risks

Environmental Awareness 91% of AIA's employees to obtain environmental awareness training by the
Increase Recycling on Airport Site end of the year 2010

Achieve a recycling rate of 50% on the airport site by the year 2012

Community Projects Promote Environmental Awareness through 12 presentations to pupils at
Water Quality Monitoring schools in the Mesogheia area
Upgrade of Vravrona Wetlands
Carbon Management Plan and Reduction Target Perform parallel analyses for STP outflow & OWMS (12 & 6 analyses
respectively) & 3 analyses at the IWTF outflow
Evaluation of the Quality of the Calibration Systems of the Air Quality
Monitoring Network (AQMN) Fencing of sensitive areas, construction of new paths, and other works at
the Vravrona wetlands

Extend AIA's participation in Airport Carbon Accreditation to Level 2
(Reduction) through the development and implementation of a multi-year
carbon management plan with a specific emission reduction target

Assess the uncertainty of the stations’ calibration systems